Construction claims and commercial consultants · Birmingham and Dubai
RKA Associates
Site team walking across a concrete slab
Claims, payment and commercial support

Construction claims consultants in Birmingham

RKA Associates are construction claims and commercial consultants. We help subcontractors get paid what they are owed, and we give main contractors and employers the commercial support to run a contract properly. NEC, JCT and FIDIC, across the Midlands, the rest of the UK and the Gulf.

Who you will deal with

  • Chartered quantity surveyorsMembers of the RICS, including MRICS, working in the UK and the Middle East
  • Commercial managers25 years and more running the commercial side of major projects
  • A quantum and delay expertQualified in law, with experience of adjudication, arbitration and dispute boards
25+ yearsCommercial and claims work on UK and Gulf projects
£1m+Claims of over £1 million prepared and negotiated
48 hoursTo reply to an enquiry, and usually much sooner
NEC · JCT · FIDICThe contracts we work under every week
Who we work for

Construction claims and commercial consultants for every side of the contract

Most of our work is for specialist subcontractors. We also act for main contractors and employers, which means we know how the other side reads your application, your notice and your claim.

01

Specialist subcontractors

Groundworks, MEICA, M&E, cladding, steel, piling and civils. You do the work well. Our commercial support and specialist subcontractor claims support make sure you get paid for it.

02

Main contractors

Cover for a busy period, or a whole project. Contract administration, supply chain accounts and claims up the line to the client.

03

Employers and clients

Developers, water companies and public bodies who want an independent view of what a contractor is entitled to, and a contract that is run by the book.

Quantity surveyors working through drawings and a valuation
From £1,690 a monthRetained QS support for subcontractors. Fees are published.
Subcontractor commercial support

A quantity surveyor for subcontractors, without the full-time salary

Most specialist contractors we work with do not need a full-time QS. They need someone who knows their contract to get the monthly application right, chase the variations and keep the final account moving. That is what outsourced commercial management in construction should do, and it is what we provide.

  • Monthly applications and interim valuations, on time and backed up
  • Variations priced and notified properly, so they get paid
  • Cost value reconciliations that show what the job is really making
  • Final accounts agreed, not left to drift for a year
The team

Senior people, doing the work themselves

You will not be passed to a junior once the work is won. The person on the first call is the person who reads your contract and writes your claim.

Commercial management and claims

NEC accredited · RICS members

More than 25 years running commercial management across water, highways, bridges and rail in the UK, Ireland and the Gulf. Contract administration, subcontractor claims, payment disputes and final accounts.

Cost and quantity surveying

Chartered quantity surveyors (MRICS)

Cost and commercial management on water infrastructure for the major UK water companies, on health, education and aviation frameworks, and on major programmes in Saudi Arabia, the UAE and Qatar.

Quantum and disputes

MRICS · MCIArb · RICS Accredited Mediator

Independent quantum and delay expert evidence, written and oral, in adjudication, arbitration and dispute board proceedings in the UK, Europe and the Middle East.

More about RKA Associates

Results

Recent outcomes

Anonymised to protect the clients involved. Each one was won on the contract and the records, not on volume.

Read the case studies
Subcontractor · NEC4£285,000Recovered in 18 days

Three months of applications refused with no valid pay less notices. Referred to adjudication and awarded in full.

Groundworks, water infrastructure, West Midlands
Main contractor · NEC4£540,000Settled by negotiation

A 14-week delay caused by late employer information, set out as compensation events with a delay analysis and prolongation costs.

Infrastructure, East Midlands
Developer · JCT D&B£720,000Saved against the sum claimed

A £1.1 million contractor claim assessed independently. Valid entitlement was £310,000 and the matter settled at £380,000.

Commercial development, West Midlands
How it works

What happens when you call

Call or send the paperwork

The subcontract, your applications, any notices and the emails that matter. The first conversation costs nothing.

An honest view

We tell you whether you have a case, roughly what it is worth and what it would cost to pursue. Sometimes the answer is that it is not worth it.

A written proposal

You get a fee proposal before any chargeable work starts. Adjudication is priced by stage, and you can stop after any of them.

The work gets done

The consultant you spoke to does the work, keeps you updated and tells you early if anything changes.

Sectors

Infrastructure, utilities and building

Our background is in civil engineering and infrastructure, and a good deal of our work is in the water sector, including the AMP8 frameworks. We work just as often on commercial building and fit-out.

  • Water and wastewater
  • AMP8 frameworks
  • Highways
  • Rail
  • Civil engineering
  • Utilities
  • Building and fit-out
  • Data centres
  • Ports and pipelines
Where we work

Midlands based, UK wide

Our office is in Birmingham city centre and most of our site work is in the Midlands. We act as claims consultants UK wide, and our Dubai base covers FIDIC work across the Gulf.

Common questions

Questions we are asked most

How much does a construction claims consultant cost?

In the UK, claims consultants usually charge somewhere between £400 and £1,200 a day, depending on seniority and how complex the dispute is. Our claims preparation rate is £450 a day, and we price adjudication by fixed stage so you know the cost before you start. Every engagement begins with a written fee proposal. Our fees page sets out the full rates.

What can I do if my main contractor won't pay?

First check whether a valid payment notice or pay less notice was served on time. If neither was, the sum in your application is usually the notified sum and is due in full. From there the options are a formal demand, a notice of intention to suspend, statutory interest and, if needed, adjudication. Our page on payment disputes goes through each step.

How long do I have to notify a compensation event?

Under NEC4 ECC clause 61.3 the Contractor has eight weeks from becoming aware of the event. Miss it and, for most events, there is no change to the Prices or the Completion Date. Many NEC subcontracts shorten that period, so check your own contract data and any Z clauses.

Can I stop work if I am not paid?

Yes, if the notified sum has not been paid by the final date for payment. Section 112 of the Construction Act gives you the right to suspend some or all of your work, but you must give at least seven days' written notice stating the grounds first. You are then entitled to an extension of time and your reasonable costs of suspending and starting again. Walking off site without following that process is a different thing and can put you in breach.

Do you only work in Birmingham and the Midlands?

No. We are based in Birmingham and much of our work is in the Midlands, but we act for clients across the UK, including Yorkshire, the North West and London. A lot of claims work can be done remotely from the documents, with site visits when they add something. We also work on FIDIC projects in the UAE, Saudi Arabia and Qatar.

More questions and answers

Contact

Speak to a consultant

Send us the outline and a senior consultant will come back to you within 48 hours, usually sooner. You will speak to the person who would do the work, and you will get a straight answer on whether it is worth pursuing.

Send an enquiry

A senior consultant will reply within 48 hours, usually sooner, with a view on where you stand and what it would cost to take further.

We only use these details to reply to you. See our privacy notice.