Construction Claims Consultant Fees and Day Rates

What we charge, how we charge it, and what you get for it. Published because being asked to guess is the thing clients tell us they dislike most about hiring consultants.

The short answer

Construction claims consultants in the UK typically charge between £400 and £1,200 per day, depending on seniority, the complexity of the dispute and how quickly the work is needed. Expert witness work and large forensic delay analyses sit at the upper end. Routine outsourced quantity surveying is a different job and a cheaper one, typically £350 to £800 a day, and is more often taken as a monthly retainer than by the day.

RKA Associates work on three bases: a day rate for advisory and claims work, a fixed fee for defined adjudication stages, and a monthly retainer for ongoing commercial management. Every engagement starts with a written fee proposal, and the first conversation is free.

Our rates

RKA Associates indicative fees by service type
ServiceBasisIndicative fee
Claims preparationDay rate£450 per day
Adjudication (referring or responding)Fixed fee per stagefrom £560 per stage
Forensic delay analysisDay rate£730 per day
Expert witness (quantum)Day rate£960 per day
Outsourced QS for subcontractorsMonthly retainerfrom £1,690 per month
Retained commercial managementMonthly retainerfrom £2,700 per month
Contract or claim reviewFixed fee£510
Initial consultationNoneFree, no obligation

Where a rate sits in those ranges reflects the work rather than the client: routine claims preparation towards the lower end, forensic delay analysis and expert witness work towards the top, which is how the market prices them and how an adjudicator or a court would expect to see them priced. Rates are exclusive of VAT and disbursements. Travel within the West Midlands is not charged. Travel beyond it is charged at cost and agreed in advance.

Fixed fees for adjudication

Adjudication is the one area where a day rate genuinely does not help you decide, because you cannot know at the outset how many days it will take. So we price it by stage, and you can stop after any stage.

StageWhat happensFixed fee
1. Merits reviewWe read the contract, the payment history and the correspondence, and tell you honestly whether you have a case worth referring.£560
2. Notice and referralNotice of adjudication, nominating body application, and the referral notice with supporting documents.£1,690
3. Reply and conductReply to the response, any further submissions the adjudicator directs, and managing the timetable to the decision.£1,970
4. Enforcement supportAssistance if the losing party does not pay and enforcement proceedings become necessary.£840

A straightforward payment adjudication taken all the way to a decision is therefore £4,220 in our fees, and most stop there because most get paid. The adjudicator's own fee is separate and is not ours to set. Adjudicators typically charge £200 to £350 per hour, and a straightforward payment dispute commonly lands somewhere between £3,000 and £8,000 in adjudicator fees. The decision will normally say who pays it.

What a day actually includes

A day is a working day of substantive work on your matter, recorded and reported. It includes reading in, drafting, calls with your team, and correspondence. It does not include:

  • The first conversation, which is free and often long enough to tell you whether you need us at all
  • Short follow-up calls and emails on a live engagement, which we do not clock-watch
  • Travel time within the West Midlands
  • Any work you have not agreed to in writing first

How to keep the fee proportionate

Being straightforward about this costs us work occasionally, and we would still rather say it.

  • Come early. The cheapest claim is one notified on time. A compensation event notified inside the eight weeks under NEC4 clause 61.3 costs a fraction of a claim we have to argue is not time-barred.
  • Bring your records, not your narrative. If your allocation sheets, site diaries and marked-up drawings are in order, we spend our time building the claim rather than reconstructing the history. Records are usually 70% of the cost of a claim.
  • Do not adjudicate small sums on principle. Below roughly £15,000, the combined cost of the adjudicator and both sides' representation often exceeds what is in dispute. We will tell you when negotiation is the better commercial answer.
  • Ask us to review, not to run. If you have a competent commercial team, a day of review on a claim they have drafted is frequently better value than handing the whole thing over.

Why we publish this

Most consultancies in this field will not put a number on a page. We think the reluctance mostly protects the consultant. If you are a subcontractor deciding whether £40,000 of unpaid variations is worth pursuing, you need to be able to do that arithmetic before you pick up the phone, not after a chargeable meeting.

Fee questions we get asked

Between £400 and £1,200 per day is the normal market range for claims work, driven by seniority, the complexity of the dispute and urgency. Expert witness and forensic delay work sits at the top of that range. Routine outsourced quantity surveying is separate and cheaper, typically £350 to £800 a day. Our own rates are £450 a day for claims preparation, £730 for forensic delay analysis, £960 for expert witness work, and retainers from £1,690 a month. Adjudication is priced by fixed-fee stage rather than by the day, so the cost is knowable in advance.
No, and it is worth understanding why. A contingency arrangement gives the consultant an interest in the size of the claim rather than in whether it is sound, which is precisely the wrong incentive when your credibility in front of an adjudicator is the asset that wins the case. It also tends to produce inflated applications that invite a true value adjudication in response. We would rather charge a fee and tell you when a claim is weak.
Three separate costs. Your representation, the adjudicator's fee, and your own management time. Our fees for a straightforward payment adjudication run to £4,220 across the three stages to a decision. The adjudicator commonly costs a further £3,000 to £8,000, and the decision usually allocates that between the parties, so budget somewhere between £7,220 and £12,220 in total. Under section 108A of the Construction Act each party generally bears its own representation costs whatever the outcome, so a party's own legal or consultancy fees are not normally recoverable in the adjudication itself.
Yes, and it is a real conversation rather than a sales call. We will look at your contract and payment position and tell you whether you have something worth pursuing. If the answer is that you do not, or that you can handle it yourself with one of our free templates, we will say so.
For defined pieces of work, yes. Adjudication stages, contract reviews and claim reviews are all quoted as fixed fees. Open-ended commercial management and claims that depend on how the other side behaves are harder to fix fairly, so those run on a day rate or a monthly retainer with an agreed cap.
For most SME subcontractors, yes. A full-time commercial manager or senior QS costs a salary plus employer's NI, pension, holiday cover, software and recruitment. A retained arrangement gives you the same expertise for the days you actually need it, scales up during a dispute and down when the workload is routine, and carries no notice period.