NEC contract administration for contractors, subcontractors and employers on NEC3 and NEC4. Compensation events notified in time, quotations that get accepted, early warnings and programmes kept up to date, so entitlement is not lost to the clock.

  • ECC, ECS and ECSC
  • Options A, B and C
  • Water, highways and rail

Speak to a consultant

A senior consultant will reply within 48 hours, usually sooner, with a view on where you stand and what it would cost to take further.

We only use these details to reply to you. See our privacy notice.

NEC contracts are built around time limits. Two weeks to reply, three weeks for a quotation, eight weeks to notify. They are designed to deal with change as it happens rather than at the end of the job. That works well when both sides keep up. When one side does not, money and time are lost to the procedure rather than the merits.

We run NEC administration for contractors and subcontractors, or support the team you have. Our directors have used NEC for years on water, highways and bridge schemes, including Option C frameworks in the water sector such as AMP8.

NEC4 compensation events

A compensation event is the NEC route to more time and money. The procedure is short and strict.

  1. Notify. The Contractor notifies within eight weeks of becoming aware of the event under clause 61.3. Late notification usually means no change to the Prices or the Completion Date. This is the NEC4 8 week time bar.
  2. Instruction to quote. The Project Manager replies within one week and, if it accepts the event, instructs a quotation.
  3. Quotation. Submitted within three weeks under clause 62.3, showing the change to the Prices and any delay to completion, with the programme.
  4. Reply. The Project Manager replies within two weeks. If it does not, the Contractor can notify the failure, and silence for a further two weeks means the quotation is treated as accepted under clause 62.6.
  5. Implementation. The event is implemented and the Prices and dates change.

Compensation event assessment is on Defined Cost plus the Fee, forecast where the work is still to be done. The dividing date under clause 63.1 separates actual cost from forecast cost, and getting it wrong is a common reason quotations are rejected.

How to notify a compensation event

A notification does not need to be long, and it does not need the cost. It needs to identify the event, say that you consider it a compensation event and give the clause. Send it through the communication system the contract requires, separately from other communications. Our guide on how to notify a compensation event goes through it step by step.

The NEC4 eight-week time bar

The eight weeks run from when you became aware of the event, not from when you worked out what it would cost. Notify early on incomplete information. The quotation can follow.

NEC early warning notices

Under NEC4 clause 15, both parties must give an early warning of anything that could increase the Prices, delay completion or affect the works. Matters are added to the Early Warning Register and discussed at early warning meetings.

An NEC early warning notice is not an admission of fault. Failing to give one can be expensive: if an experienced contractor could have warned and did not, the compensation event is assessed as if it had. Our guide to NEC4 early warnings explains how to use them.

NEC programme acceptance

The Accepted Programme is the baseline every compensation event is measured against. Under NEC4 the Project Manager has two weeks to accept or reject a programme under clause 31.3, and if it fails to respond the Contractor can notify the failure and the programme is treated as accepted a week later. NEC3 has no deemed acceptance, which is one of the main reasons NEC3 projects end up with no accepted programme at all.

Where no programme was identified in the Contract Data, a quarter of the Price for Work Done to Date can be retained until the first programme is submitted. Keep the programme current. A compensation event assessed against an old programme is usually assessed wrongly.

Compensation events under Options A, B and C

  • Option A, priced contract with activity schedule. Compensation events change the activity schedule prices, assessed on Defined Cost plus Fee. The Contractor carries the risk on everything else.
  • Option B, priced contract with bill of quantities. Changes in quantities are not usually compensation events unless they cross a threshold or the bill is wrong.
  • Option C, target contract with activity schedule. Compensation events change the target. Defined Cost is paid as incurred, and the difference between final cost and target is shared. Every compensation event moves the pain and gain, so the target needs managing as closely as the cost.

NEC subcontract support

For an NEC4 ECC subcontractor, the subcontract is usually the NEC4 Engineering and Construction Subcontract (ECS) or the shorter NEC4 ECSC. They mirror the main contract, but many are amended with Z clauses that shorten your notice periods so the main contractor can notify upwards in time. Some remove deemed acceptance altogether. Check your Z clauses before you rely on the standard periods. We review NEC subcontracts as part of our contract review service.

NEC3 compensation events

NEC3 is still in use on many frameworks. The compensation event procedure is broadly the same, with the eight-week bar under clause 61.3, but there are differences that catch people out, including the programme rules and the Risk Register. Our NEC3 guide sets them out side by side with NEC4.

NEC consultant in Birmingham, working UK wide

We are based in Birmingham and support NEC projects across the UK. Much of our NEC work is on water and wastewater frameworks, highways and civils, but the same procedures apply to building projects. If you want to prepare a quotation yourself, our Datum compensation event tool walks you through it.

Questions

How long do I have to notify a compensation event?

Eight weeks from becoming aware of the event under NEC4 and NEC3 clause 61.3. Events the Project Manager should have notified, such as its own instructions, are not caught by the bar. Subcontracts are often amended to shorten the period, so check yours.

What happens if the Project Manager does not reply to a quotation?

Under NEC4 the Contractor can notify the Project Manager of its failure to reply. If there is still no reply within two weeks of that notice, the quotation is treated as accepted. The notice of failure is essential. Without it there is no deemed acceptance.

Is an early warning an admission of fault?

No. It is a notice that something might affect cost, time or quality. Giving one protects you, because failing to give one can reduce what you recover on a related compensation event.

Do NEC subcontracts have the same time limits as the main contract?

The standard ECS mirrors the ECC, but many subcontracts are amended to give the subcontractor shorter periods. Read the Z clauses and the subcontract data, because the amended periods are the ones that apply.

Compensation event close to the eight-week line?

Call today. A short notice issued now is worth more than a perfect one issued next week.