NEC3 contracts: compensation events, early warnings and the differences from NEC4

NEC3 compensation events, early warnings and programme rules, and the differences from NEC4 that matter: time bars, quotations, Risk Register, final account.

By RKA Associates6 minute readUpdated October 2026

NEC3 is still in use on a great many UK projects, even though NEC4 replaced it in June 2017. If your contract is NEC3, most of the compensation event procedure is the same as NEC4, including the eight-week time bar in clause 61.3. Several things are not. There is no deemed acceptance of a programme, early warnings sit on a Risk Register under clause 16, the cost of preparing quotations is not recoverable under Options A and B, and there is no final assessment procedure. Working an NEC3 contract from an NEC4 guide is how entitlement gets lost.

Why NEC3 is still around

Construction contracts outlive their editions. Frameworks and term service contracts let on NEC3 before 2017 have often run for years since, projects started under NEC3 are still being completed and argued over, and some clients stayed with the form their teams knew. Subcontracts placed under an NEC3 main contract are usually NEC3 as well, and a mismatch between an NEC3 main contract and an NEC4 subcontract, or the other way round, is a reliable source of disputes about notices and timescales.

Compensation events under NEC3

NEC3 lists nineteen compensation events in clause 60.1. The procedure runs as follows.

  • Notification, clause 61.3. The Contractor notifies within eight weeks of becoming aware of the event, or loses the entitlement, unless the Project Manager should have notified it and did not. The same bar as NEC4.
  • The Project Manager's reply, clause 61.4. Within one week, or a longer period the Contractor agrees. If the Project Manager does not reply, the Contractor can notify that failure, and if it continues for a further two weeks the event is treated as accepted and as an instruction to submit quotations.
  • Quotations, clause 62.3. The Contractor submits within three weeks of being instructed to, and the Project Manager replies within two weeks.
  • Deemed acceptance, clause 62.6. If the Project Manager does not reply to a quotation in time, the Contractor can notify that failure; if there is still no reply within two weeks, the quotation is treated as accepted.
  • Assessment, clause 63.1. Changes to the Prices are assessed on the effect on Defined Cost plus the Fee. Under NEC3 the dividing line between actual and forecast cost is the date the Project Manager instructed, or should have instructed, the Contractor to submit quotations. NEC4 replaced that with a defined "dividing date".

Two NEC3 points catch people out. Under Options A and B, the cost of preparing quotations is excluded from Defined Cost, so the time spent pricing a compensation event is not recoverable. And if the Project Manager has notified that the Contractor did not give an early warning it should have given, the event is assessed as if the warning had been given, under clause 63.5.

Early warnings and the Risk Register

Under NEC3 early warnings are in clause 16. The Contractor and the Project Manager each give an early warning of matters that could increase the Prices, delay Completion or a Key Date, or impair the performance of the works. The Project Manager enters them on the Risk Register, and either can instruct the other to attend a risk reduction meeting. NEC4 moved early warnings to clause 15, renamed the register the Early Warning Register, and made the Project Manager issue the first register and hold the first meeting within set periods of the starting date. Our guide to early warnings covers the practice, which is the same under both.

The programme

Under NEC3 clause 31.3 the Project Manager accepts a programme or gives reasons for not accepting it within two weeks. There is no deemed acceptance; if the Project Manager says nothing, the remedy is a compensation event under clause 60.1(6) for failing to reply. Until the first programme showing the information the contract requires has been accepted, clause 50.3 lets the Project Manager retain a quarter of the Price for Work Done to Date. NEC4 added the deemed acceptance mechanism: notify the failure and, after a further week, the programme is treated as accepted.

NEC3 and NEC4: the differences that matter in practice

Differences between NEC3 and NEC4 ECC
SubjectNEC3NEC4
Parties and documentsEmployer; Works InformationClient; Scope
Early warningsClause 16, Risk Register, risk reduction meetingsClause 15, Early Warning Register, early warning meetings
Compensation eventsNineteen in clause 60.1Two more: 60.1(20) and 60.1(21)
Eight-week time barClause 61.3Clause 61.3, unchanged
Cost of preparing quotationsExcluded under Options A and BRecoverable
Actual and forecast costSplit at the instruction to quoteSplit at the dividing date
Programme not answeredCompensation event, 60.1(6)Treated as accepted, 31.3
Final accountNo final assessment procedureFinal assessment, clause 53
DisputesW1 or W2W1, W2 or the new W3 dispute avoidance board

Working an NEC3 contract well

  • Read the contract you signed, not the one you are used to. Clause numbers moved between editions, and notices that cite the wrong clause invite argument.
  • Keep the eight-week diary for every event from the day you become aware of it, exactly as you would under NEC4.
  • Chase silence in writing. NEC3 gives you deemed acceptance of compensation events and quotations, but only if you notify the Project Manager's failure.
  • Keep the programme current and submitted. Without an accepted programme, compensation events are assessed against whatever the Project Manager decides is reasonable.
  • Check the subcontract periods. Main contractors often shorten the subcontract timescales so they can meet their own, and an NEC3 subcontract under an amended main contract can carry tighter deadlines than the standard form.

Our guides to compensation events and notifying one apply to NEC3 as well as NEC4, with the differences above. We work on NEC3 and NEC4 contracts, including the Engineering and Construction Subcontract and the Term Service Contract; see NEC contract administration.

NEC3 questions

Is NEC3 still used?

Yes. NEC4 was published in June 2017, but NEC3 is still in use on projects that were let under it and on long-running frameworks and term contracts that adopted it before NEC4 existed. Subcontracts placed under an NEC3 main contract are often NEC3 too.

Is the eight-week time bar the same under NEC3 and NEC4?

Yes. Under clause 61.3 of both, a Contractor who does not notify a compensation event within eight weeks of becoming aware of it loses any change to the Prices, the Completion Date or a Key Date, unless the Project Manager should have notified the event and did not.

Does NEC3 have deemed acceptance of the programme?

No. Deemed acceptance of a programme is new in NEC4, under clause 31.3. Under NEC3, if the Project Manager does not reply to a programme within the two weeks allowed, the remedy is a compensation event under clause 60.1(6) for failing to reply within the period required.

Can I recover the cost of preparing a quotation under NEC3?

Not under Options A and B, where NEC3 excludes the cost of preparing quotations for compensation events from Defined Cost. NEC4 removed that exclusion.

What is the Risk Register in NEC3?

The register of early warnings kept by the Project Manager under clause 16 of NEC3, reviewed at risk reduction meetings. NEC4 renamed it the Early Warning Register, moved early warnings to clause 15 and renamed the meetings early warning meetings.

Do you work on NEC3 contracts?

Yes. We notify and price compensation events, prepare and defend claims and administer contracts under NEC3 and NEC4, including the Engineering and Construction Subcontract and the Term Service Contract.

Contact

Speak to a consultant

Send us the outline and a senior consultant will come back to you within 48 hours, usually sooner. You will speak to the person who would do the work, and you will get a straight answer on whether it is worth pursuing.

Send an enquiry

A senior consultant will reply within 48 hours, usually sooner, with a view on where you stand and what it would cost to take further.

We only use these details to reply to you. See our privacy notice.