Most of the disputes we deal with were decided when the subcontract was signed. A seven-day notice period nobody noticed, a payment clause tied to the main contract, a set-off right with no limit. By the time the problem appears, the clause has been in the contract for months.
Contract checking for subcontractors is one of the cheapest things we do and one of the most useful.
What a subcontract review covers
We read the subcontract, the schedule of amendments and the documents it refers to, and give you a short written report. It lists the clauses that carry real risk, explains what each would mean on site in plain terms, and suggests wording to ask for instead. A standard review is a fixed fee of £510.
Onerous subcontract terms we see most often
- Payment linked to the main contract. Pay when certified, or retention released only at main contract completion.
- Short notice periods. Delay and variation notices due within days, often as conditions precedent.
- Wide set-off rights. Deductions for losses on other contracts, or without notice.
- Uncapped liquidated damages. Or damages tied to the main contract rate, which can be far larger than your subcontract value.
- Fitness for purpose design. Under DBSub and similar forms, a shift from reasonable skill and care.
- Back-to-back clauses. Making your entitlement depend on what the main contractor recovers from the employer.
- Termination for convenience. With no payment for loss of profit on the work removed.
- Discounts and charges. Main contractor's discounts, attendance charges and contributions to site costs.
Z clauses in NEC subcontracts
NEC Z clauses are additional conditions that change the core clauses. On subcontracts they are used to shorten notification and reply periods, remove deemed acceptance, delete compensation events from the list and move risk down the chain. Some are reasonable. Some remove most of the protection the standard form gives you. We read the Z clauses against the core clauses so you can see exactly what has changed.
Letter of intent risks
Starting on a letter of intent is common and sometimes unavoidable. The risks are that the letter caps what you can recover, that it does not say which terms apply, or that the parties never sign the subcontract and later disagree about whether one exists. In RTS Flexible Systems v Molkerei Alois Müller [2010] the Supreme Court found a contract on terms the parties had not signed, because of how they behaved. Make sure the letter sets a sensible cap, describes the work and says how you will be paid if the subcontract is not signed.
Subcontract negotiation
Main contractors will negotiate more than most subcontractors expect, particularly on payment terms, notice periods, caps and set-off. They rarely move on everything. We help you pick the few changes that matter most and ask for them clearly, ideally at tender stage, when you are in the strongest position to ask.
Subcontractor termination
Ending a subcontract is a serious step and has to be done exactly as the contract says, or under the general law. Most subcontracts allow termination for specified defaults, usually after a warning notice and a period to put things right. The notices have to be served in the right form, to the right address and at the right time. Getting the procedure wrong can turn a valid termination into a wrongful one.
Repudiatory breach of contract
A repudiatory breach is one serious enough to show that a party no longer intends to be bound by the contract. The innocent party can accept it and bring the contract to an end, or carry on and claim damages. Non-payment on its own is not usually enough. Persistent non-payment combined with other conduct can be. These are judgement calls on the facts, and you should get advice before you act on one.
Walking off site
When you are not being paid, walking off site can feel like the only lever left. It is also the step most likely to turn a strong position into a weak one. If you leave without a contractual or legal right to, you may be the party in repudiatory breach, and the main contractor will claim the cost of replacing you.
The Construction Act gives you a safer route. You can suspend work for non-payment of the notified sum after seven days' written notice, and you are entitled to the time and cost. See our page on payment disputes for how it works.
Project rescue
Sometimes a job is not yet at the point of termination but is clearly heading there: payments slipping, variations unagreed, programme falling apart and relationships breaking down. We come in, get the records, programme and account in order, put the correct notices in place and give you a clear plan. Most projects can be brought back if this happens early enough.
Questions
Should I start work on a letter of intent?
It is often unavoidable, but read it first. Check the cap, the scope, which terms apply and how you will be paid if the subcontract is never signed. If the cap is too low, ask for it to be increased before you reach it.
Can I walk off site if I am not being paid?
Not without risk. The safer route is to suspend under section 112 of the Construction Act after giving seven days' written notice. Leaving site without that process, or a clear right to terminate, can put you in breach yourself.
What is a Z clause?
An additional condition in an NEC contract that amends the standard clauses. Subcontracts often use them to shorten time limits and move risk to the subcontractor, so they should always be read before signing.