NEC4 compensation event tool for subcontractors

Build your compensation event quotation now

No charge, no sign up, works on a phone. Around twenty minutes from a blank page to a draft you can issue. Nothing you enter leaves your own browser.

Why compensation events get rejected

Most subcontractors do not lose compensation events on the merits. They lose them on the paperwork. The notice goes in late, or never goes in at all. The quotation does not say which part of clause 60.1 it relies on. The cost is built up from tender rates instead of Defined Cost. The delay is asserted but never tied back to the Accepted Programme. By the time anyone looks at it properly, the money has gone.

None of that is a lack of ability. It is a lack of time. A subcontractor running four or five live packages with no quantity surveyor is not going to sit down and work methodically through clause 60 to 65 for every change that lands on site. So the small events get let go, and the big ones get submitted in a form the main contractor can pick apart.

Datum is our answer to that. It asks the questions a quantity surveyor would ask, in the order we would ask them, and turns the answers into a quotation. There is no charge to use it, and you can have a chartered surveyor review and sign off the result before it goes anywhere.

How the tool works

Seven steps, about twenty minutes, no contract knowledge assumed.

  1. The subcontract. Which form you are under and on which main option. That decides whether your Defined Cost is built up using the Shorter Schedule of Cost Components or the full schedule.
  2. Your amendments. How your subcontract differs from the standard form. This is the step most tools skip, and the one that changes everything else.
  3. The event and the clock. What happened, when it happened and when you became aware. The tool shows you exactly where you stand against your notice period before you spend any more time on it.
  4. The clause. All twenty-one grounds in clause 60.1, written in plain English rather than contract language. Anything your amendments have deleted is shown struck through and cannot be selected.
  5. Your records. What you actually hold and could hand over tomorrow. This is what decides how far an assessment gets cut back.
  6. Defined Cost and fee. Built up by component, with the fee percentage from your Subcontract Data and a risk allowance under clause 63.8.
  7. The programme. The delay to planned Completion, measured the way clause 63.5 requires rather than the way most people assume.

At the end you get a scored assessment showing where the event is strong and where it is exposed, a recovery band in percentage terms, and a draft quotation you can copy, print or save as a PDF.

It works on amended subcontracts, not just the standard form

Almost no subcontract runs on the unamended NEC4 form. The amendments are where subcontractors lose money, and they are the reason generic contract software gives the wrong answer.

The tool asks you to record four things, all of which you will find in the Subcontract Data or the schedule of amendments:

  • The notice period. Eight weeks is the standard. Four weeks is common in subcontracts, and we see three and two. The clock on the next step rescales to whatever period you are actually working to.
  • Condition precedent wording. Language such as "shall be a condition precedent to any entitlement" turns a late notice from arguable into fatal. The assessment weighs it accordingly and the draft tells you to meet the point head on.
  • Deleted grounds. Physical conditions under 60.1(12) and adverse weather under 60.1(13) are the two most often struck out of subcontracts. If you have selected one that has gone, the tool flags it and points you towards the alternative route.
  • Caps and exclusions. Capped preliminaries, excluded head office overhead, fixed daywork rates. These appear as a warning on the cost build-up and as a note for the reviewer.

If your subcontract is genuinely bespoke rather than an amended NEC form, the numbering assumptions stop holding. Use the tool to organise the facts and the cost, then send it to us for review rather than relying on the clause references.

The review and sign-off

A draft prepared by software is still a draft prepared by software. If you want it checked, we will read it against your actual subcontract, correct the clause references for your amendments, test the cost build-up and the programme argument, and put a chartered surveyor's name to it. Turned round in two working days.

That is a fixed fee per event, quoted before any work starts, and it is a fraction of what the same event would cost on an hourly basis.

Using the tool does not make us your advisers. No professional relationship arises unless you instruct us and we confirm the engagement in writing.

Who it is for

Subcontractors and specialist contractors working under NEC4 on water, civils, highways, rail and building projects, typically turning over between £2m and £30m, with either no quantity surveyor or one who is already stretched across too many jobs. If that is you, the events you are currently letting go are worth more than you think.

It is equally useful for main contractors' commercial teams who want a consistent format for the quotations coming up from their own supply chain.

Common questions

What does it cost?

Nothing to use. Working through the steps and producing a draft carries no charge and needs no sign up. You pay only if you ask us to review and sign off the result.

Where does my information go?

Nowhere. Everything you type stays in your own browser. Nothing is sent to us, stored on a server or used to train anything. If you want us to see it, you send it to us yourself.

What is the eight-week rule?

Under clause 61.3 of NEC4, if you become aware that a compensation event has happened and do not notify it within eight weeks, you lose your entitlement to any change to the Prices, the Completion Date or a Key Date, unless the Project Manager or Contractor should have notified it and did not. Many subcontracts shorten that period. Read our fuller guide on NEC compensation events and on how to notify a compensation event.

What if I have already missed the deadline?

Notify anyway. A late notice preserves an argument; no notice removes it. Then talk to us before you spend time on the build-up, because whether it is worth pursuing depends on the wording in your particular subcontract.

Can I use it for NEC3?

The clause numbering in NEC3 is close enough that the tool is still useful, and there is an NEC3 option in the form selector. The assessment rules differ in places, so have the draft reviewed before you issue it.

Contact

Speak to a consultant

Send us the outline and a senior consultant will come back to you within 48 hours, usually sooner. You will speak to the person who would do the work, and you will get a straight answer on whether it is worth pursuing.

Send an enquiry

A senior consultant will reply within 48 hours, usually sooner, with a view on where you stand and what it would cost to take further.

We only use these details to reply to you. See our privacy notice.