JCT contracts treat time and money separately. You can be entitled to an extension of time and still not be paid for the delay, or entitled to loss and expense without the completion date moving. Each needs its own notice, its own evidence and its own claim. Many JCT disputes we see started because one of them was missed.
We prepare JCT subcontract claims and contract advice for subcontractors and main contractors on building, fit-out and civils work, mostly under Design and Build and its subcontract, DBSub.
JCT relevant events and extensions of time
A JCT extension of time depends on two things: a Relevant Event, and a delay notice that complied with the contract. Relevant Events include variations, instructions, late information, deferment of possession and acts of prevention by the employer or, in a subcontract, by the main contractor.
The notice is due when it becomes reasonably apparent that progress is being or is likely to be delayed. It should identify the cause, and you then provide particulars of the expected effect and an estimate of the delay. You are also expected to use your best endeavours to prevent delay. A delay notice that turns up at the end of the job, explaining everything in hindsight, is much easier to reject.
Our guide to JCT extension of time applications covers what the application should contain.
JCT loss and expense
Money for disruption and prolongation comes through the loss and expense provisions, triggered by Relevant Matters. These overlap with the Relevant Events but are not the same list. The application should be made as soon as it becomes reasonably apparent that you have incurred or are likely to incur direct loss and expense, with supporting information and regular updates.
Loss and expense is assessed on what you actually lost, not on your tender rates. The heads usually include time-related site costs, extended plant and supervision, disruption to labour productivity, head office overheads and finance charges. Our page on records for loss and expense sets out what each head needs.
JCT payment notices
JCT contracts follow the Construction Act payment regime closely. Each interim payment has a due date and a final date for payment, set in the contract particulars. The payer issues a payment notice, and a pay less notice if it intends to pay less than the notified sum. Your interim application stands as the default if no payment notice is served, provided you made it in time.
The notice dates in a JCT subcontract are often different from the main contract, and many main contractors amend them. Diarise yours. Our page on payment disputes explains what to do when the notices are missing or late.
JCT DBSub and design responsibility
Under DBSub the subcontractor takes on design responsibility for its portion of the works. The standard wording is reasonable skill and care, but main contractor amendments often push this towards fitness for purpose, or make you responsible for the employer's requirements as a whole. That changes the risk considerably. It is the first thing we look at when reviewing a DBSub schedule of amendments.
JCT final account
The JCT final account is built from the adjustments to the subcontract sum: variations, provisional sums, loss and expense and the rest. The final statement or final payment process can become conclusive if it is not challenged in time, so a final account should never be left sitting with a deadline approaching. We prepare and negotiate JCT final accounts, and take them to adjudication when needed. See variations and final accounts.
Amendments and the 2024 editions
Few main contractors use JCT subcontracts unamended. Common changes include shorter notice periods, wider rights of set-off, back-to-back time bars linked to the main contract and caps on extensions of time. The 2024 editions of the JCT contracts changed several standard provisions as well. Read the amendments before you price the job, not after the first dispute.
Working with a JCT contract consultant
We act for subcontractors, main contractors and employers under JCT. That means we have read the same clauses from both sides and know how each party usually argues them. For a subcontractor, our advice is usually most useful at two points: before signing, and as soon as a delay or change starts to look expensive.
Questions
How do I claim an extension of time as a subcontractor?
Give a written delay notice as soon as it becomes reasonably apparent that your progress is being or will be delayed, identifying the cause. Follow it with particulars of the effect and an estimate of the delay, and update it as things develop. Base the claim on the programme and your records, and show how the event affected your critical path.
How do I claim loss and expense?
Make a written application as soon as it becomes reasonably apparent that a Relevant Matter is causing you loss and expense. Support it with information showing the cause and the cost, and update it regularly. The claim must be based on what you actually spent and lost, from your records.
What happens if I did not send a delay notice?
Under the standard JCT wording the notice is not usually a condition precedent, so you may still get an extension, though the late notice can count against you. Amended subcontracts often turn the notice into a strict time bar. Check the wording before assuming either way.