When the main contractor stops paying
Late and short payment is the most common problem subcontractors bring to us. It strains cash flow, makes it harder to pay your own suppliers and labour, and if it goes on long enough it can put an otherwise sound business at risk.
The Construction Act gives subcontractors real remedies, but they depend on dates and paperwork, so it pays to act quickly and in the right order. These are the steps we work through when a client calls with an unpaid application.
1. Check whether a valid pay less notice was issued
Under the Construction Act (Housing Grants, Construction and Regeneration Act 1996, as amended), when you submit a payment application, the main contractor must either pay the amount you have applied for or issue a valid pay less notice by a specific date. A pay less notice must state the sum the payer considers due and set out the basis of calculation.
If the main contractor has not issued a valid pay less notice by the prescribed date, the amount in your application will generally be payable in full, whether or not they agree with it. This is the basis of what is known as a smash and grab adjudication.
Check your subcontract to find the pay less notice deadline. Under most NEC and JCT subcontracts, the deadline is a set number of days before the final date for payment. If that deadline has passed without a valid notice, your position is strong.
2. Review the payment terms in your subcontract
Before taking action, make sure you understand your subcontract payment cycle. Check when payment applications are due, what the payment notice and pay less notice deadlines are, and what the final date for payment is. Under NEC subcontracts, the payment cycle is set out in the contract data. Under JCT subcontracts, it follows the interim payment provisions.
Common mistakes subcontractors make include submitting applications late (which can affect your rights), not following the contractual format, and not including all entitled compensation events and variations. Getting the application right is the cheapest protection you have, and it is work a QS for subcontractors can take off your hands.
3. Consider adjudication
If your main contractor is refusing to pay and either has not issued a valid pay less notice or is disputing your valuation without proper basis, adjudication is usually the quickest route to being paid. The adjudicator has to reach a decision within 28 days of the referral, unless that period is extended, and the decision is binding unless it is later overturned in court or arbitration.
Adjudication is a statutory right under the Construction Act, so your main contractor cannot stop you using it, whatever your subcontract says. The process starts with a notice of adjudication, followed by a referral to the adjudicator within seven days.
A straightforward payment dispute, particularly a smash and grab where no valid pay less notice was issued, typically takes around five weeks from the notice to the decision.
4. Take advice before you stop work
It is tempting to down tools when you are not being paid. The Construction Act does give a right to suspend work for non-payment, but only after at least seven days' written notice of your intention to suspend, stating the grounds. Stopping without following that procedure, or the terms of your subcontract, can give the main contractor grounds to terminate or to counterclaim. NEC and JCT subcontracts also have their own termination provisions, which need to be followed precisely.
Speak to someone before you stop work on site.
5. Keep detailed records
Whatever route you take to recover payment, you will need evidence. Keep copies of all payment applications, any payment or pay less notices received (or evidence of their absence), all correspondence, and records of the work carried out. If the dispute escalates to adjudication, the quality of your records will shape the outcome.
How we can help
RKA Associates are construction claims consultants and quantity surveyors in Birmingham, working for subcontractors across the UK. We can review your payment position, usually within 48 hours, tell you which route makes sense, and prepare and run an adjudication if it comes to that. We work with MEICA subcontractors, groundworks contractors, M&E specialists, steelwork, cladding, piling, demolition and civils subcontractors UK wide.